Birmingham Oracle cost: why is the bill £128M?

A council report says the rebuilt system is live with no showstopper faults. The program is rated amber and managers are skipping tasks.

Grand ornate building with a dome, flag, and sculpture

The Birmingham Oracle cost, including forecast spend, is put at £128.1 million, The Register reported on November 27, against £19.96 million in the 2019 business case. The 6.4-fold gap isn't like for like: the council says its program total covers more than two implementations.

What makes up the £128M Birmingham Oracle cost?

The total covers far more than two software projects. The Register describes it as the first rollout plus this year's rebuild. The council's report to its Audit Committee on November 25 says it is not valid to equate the program total with the first implementation plus the rebuild. The report lists the first system and attempts to fix it, the rebuild, a new income management system, running costs and extra support. It also counts third-party license and support costs from 2018-19 to 2026-27. The report puts the forecast within the approved budget, and a reconciliation is being started to break down the spend. The Register says the funding allocation had previously reached £157 million.

How did the first rollout go wrong?

The first system arrived late and then ran into serious trouble. Work began in 2019 with go-live planned for April 2021, but the council started using it in April 2022. The Register reports that more than £5 million went on manual workaround labor. It also notes that the early budget was meant to cover schools, which the rebuild leaves out. A 2024 analysis by the Audit Reform Lab at the University of Sheffield estimated the direct and indirect impact would reach £216.5 million by April 2026.

Is the rebuilt Oracle system working now?

Yes, by the council's account, with work left to do. The rebuilt system went live in August with no priority one faults, and has since completed three payroll runs and three finance month ends. Three priority two incidents have occurred and one is open, on ending or extending contingent and fixed-term contracts, where the council says the technical fault is fixed and process compliance remains. Hypercare ended on November 20. Open support tickets stood at 372 on November 10, under a target ceiling of 400, for a user base of 12,500. The program is rated amber.

Why are commissioners still concerned?

They call it a successful technical implementation but worry the council may struggle to adopt the controls and processes the system brings. The report gives an example. For 193 fixed-term and contingent workers whose contracts were due to end or be extended in November, 149 cases had no manager tasks actioned in the system, and mitigations are in place so people aren't wrongly cut off. Only 37% of managers had attended the overview manager course, and 16% of colleagues the employee self-service one. The council notes that attendance at those courses was self-selected and other training material was available.

What happens next for the program?

Handover to long-term support runs in two stages. Version 1 is due to start as support partner on December 1, with the first gate scheduled for early December. The second, full transfer to an in-house Center of Excellence, is due in early March 2027. A staff consultation on that team's structure runs into December, and the report flags a risk that knowledge isn't passed on properly before the program closes, with some permanent roles unfilled. More than 300 possible enhancements are waiting for a priority call.

What should IT and finance teams check before an ERP deal?

Price the whole life of the system and the change work around it.

  • Separate license, support, build, workaround labor and rework in one budget view.
  • Name who pays if go-live slips, and what running the old system costs.
  • Test payroll, bank reconciliation and month end before sign-off.
  • Measure manager task completion and training attendance from week one.
  • Fund and fill the support team before the project staff leave.

What IT will ask you to prove: that income management and bank reconciliation are designed and costed, which integrations are inside scope, who holds Oracle skills after handover, and how quarterly updates will be tested. Ask the supplier for its security review, single sign-on setup and data location in writing.