JERA data center talks: which tech firms are involved?
Japan's largest power generator wants data centers built beside its plants around Tokyo. The talks are reported. An October memorandum with Dell and RHAELM, first planned for Chiba, is signed.

JERA data center talks involve Anthropic, Meta, Amazon, Microsoft and Google, Nikkei reported on November 27, 2026. Japan's largest power generator wants to build the sites next to power plants around Tokyo. No agreement with any of the five companies has been announced.
Which tech companies are in the JERA data center talks?
Five US companies are named: Anthropic, Meta, Amazon, Microsoft and Google. Nikkei Asia reported that JERA's chief told it about talks with Anthropic, Meta and other US technology companies on data centers beside power plants around Tokyo. Reuters, citing Nikkei, identified him as Global CEO and Chair Yukio Kani.
Nikkei's Japanese report added that JERA has also opened negotiations with Amazon, Microsoft and Google. It said JERA is trying to reach agreements by offering the advantage of drawing electricity directly from a power plant attached to the site.
The readable portions of Nikkei's reports don't give a capacity, price or date for any of these talks, or say which company is furthest along.
Has any JERA data center deal been signed?
No deal with any of the five companies has been announced. Reuters, which relayed the Nikkei report, got no immediate comment from JERA or from any of the five companies.
JERA has already signed a memorandum of understanding (MoU). On October 1, it agreed with Dell Technologies and RHAELM Holdings, a developer of AI infrastructure, to build a standard framework for national-scale AI infrastructure in Japan. The first use is planned for a project in Chiba, near Tokyo. The announcement says Apollo Global Management intends to be RHAELM's strategic investment and financing partner on that project.
The October announcement does not name any of the five companies as a tenant, and the pages we read don't say whether the new talks involve the Chiba site. Treat the talks as early until terms are confirmed.
What is planned at the JERA, Dell and RHAELM site in Chiba?
The Chiba project is an AI data center supported by up to 400 megawatts of power capacity at JERA's Chiba Thermal Power Station. JERA and RHAELM are developing it, and RHAELM leads delivery. JERA provides power and land beside its stations, while Dell supplies standardized rack-scale AI systems.
Total spending across all phases is expected to pass $15 billion, or 2.3 trillion yen, covering land, power infrastructure, construction and computing equipment. Operations are targeted to begin around 2028.
At 400 megawatts, the companies said, it would be Japan's largest AI infrastructure deployment on a single site. JERA and RHAELM also intend to explore other JERA locations, with an ambition of several gigawatts of capacity across Japan in the 2030s.
Why build a data center behind the meter?
In JERA's plan, a behind-the-meter site draws on the company's operating power plant next door, which JERA says saves years. Its October announcement said the Chiba design can deliver capacity "years ahead" of the usual timeline for a grid-connected project. That is the company's own projection for a project that is not yet operating.
JERA says it produces one-third of Japan's electricity, and Kani said in the October announcement that it supplies nearly all the power used in the Tokyo metropolitan area. The company also buys, ships and regasifies liquefied natural gas (LNG).
The same announcement tied the speed of Japan's AI buildout to dependable gas-fired power and a sturdy LNG supply chain. Buyers with emissions targets should factor the gas supply into their review.
What should buyers of Japan data center capacity do now?
Buyers of data center capacity in Japan should treat the talks as a signal and keep current plans in place. Neither the reported talks nor the October announcement describes capacity you can contract today. These steps are our suggestions.
- Ask your cloud or AI provider whether its Japan roadmap depends on any JERA site.
- Plan next year's workloads around capacity that exists, because Chiba operations are targeted for around 2028.
- Ask developers what backs up a behind-the-meter site when its power plant or fuel supply is interrupted.
- Request the energy mix and emissions reporting for any gas-powered capacity.
- Watch for a named tenant, a signed power agreement and a construction start before you count on the dates.
Related: why Asian data center loans are stalling, AWS plans for a former Pennsylvania coal plant.